Schedule

To protect the City’s investment and minimize risks, construction will be completed in three phases. Schedules for the three phases overlap to maintain an aggressive schedule and minimize the overall construction duration.

Phase 1: Lift Station 87 Microtunneling

This critical project element began in January 2017 and was completed in June 2017.

Phase 2: Lift Station 87 Structure

Pre-construction work began in October 2017. Construction of Lift Station 87 is expected to be completed in mid-2020.

Phase 3: Open Cut Pipeline Installation

The construction schedule for this phase will be known once a contractor is on board, but is tentatively scheduled to begin in early 2020 and be completed by the end of 2020.

Leave a Reply