Schedule

To protect the City’s investment and minimize risks, construction will be completed in three phases. Schedules for the three phases overlap to maintain an aggressive schedule and minimize the overall construction duration.

Phase 3: Open Cut Pipeline Installation Sequencing & Scheduling

Date Updated: December 12, 2020
The following dates are estimated and subject to change based on weather, unforeseen conditions, or accommodations:

Gravity Sewer Connections on Alta Vista between Osprey Ave and Pomelo Ave:

Address:                                                                      Date:

1002 Alta Vista St. & 986 Alta Vista St.                    1/26/2021

1776 Alta Vista St. & 1777 Alta Vista St.                  2/1/2021

1774 Alta Vista St. & 1763 Alta Vista St.                  2/4/2021

1753 Alta Vista St.                                                    2/10/2021

1750 Alta Vista St.                                                    2/17/2021

1743 Alta Vista St. & 1742 Alta Vista St.                  2/22/2021

1741 Alta Vista St. & 1734 Alta Vista St.                  3/6/2021

1720 Alta Vista St. 1731 Alta Vista St.                      3/15/2021

1717 Alta Vista St.                                                    3/17/2021

1700 Alta Vista St. & 1703 Alta Vista St.                  3/25/2021

*Reclaimed water main to be installed after the gravity sewer.

 

Gravity Sewer Connections on Pomelo Ave & Pomelo Place:

Address:                                                                                      Date:

939 Pomelo Pl to 959 Pomelo Pl                              1/7/2021 to 2/10/2021

904 Pomelo Ave to 950 Pomelo Ave                         2/10/2021 to 3/5/2021

Alta Vista & Pomelo Ave to 960 Pomelo Ave            4/12/2021 to 4/26/2021

Manhole at Pomelo Ave & Pomelo Place                 4/26/2021 to 4/29/2021

*Watermain, reclaimed water, and stormwater pipes to be installed after the gravity sewer.

 

Phase 2: Lift Station 87 Structure

Pre-construction work began in October 2017. Lift Station 87 became operational in October 2020.  Final completion scheduled for November 2020.

Phase 1: Lift Station 87 Microtunneling

This critical project element began in January 2017 and was completed in June 2017.