To protect the City’s investment and minimize risks, construction will be completed in three phases. Schedules for the three phases overlap to maintain an aggressive schedule and minimize the overall construction duration.
Phase 3: Open Cut Pipeline Installation Sequencing & Scheduling
Date Updated: 5 March, 2021
The following dates are estimated and subject to change based on weather, unforeseen conditions, or accommodations:
Gravity Sewer Connections on Alta Vista between Osprey Ave and Pomelo Ave:
Address: Date:
1002 S. Osprey & 986 S. Osprey Complete
1776 Alta Vista St. & 1777 Alta Vista St. Complete
1774 Alta Vista St. & 1763 Alta Vista St. Complete
1753 Alta Vista St. 3/11/2021
1750 Alta Vista St. 3/18/2021
1743 Alta Vista St. & 1742 Alta Vista St. 3/26/2021
1741 Alta Vista St. & 1734 Alta Vista St. 4/9/2021
1717 Alta Vista St. 1731 Alta Vista St. 4/19/2021
1720 Alta Vista St. 4/22/2021
1700 Alta Vista St. & 1703 Alta Vista St. 5/3/2021
*Reclaimed water main to be installed after the gravity sewer.
Gravity Sewer Connections on Pomelo Ave & Pomelo Place:
Address: Date:
939 Pomelo Pl to 959 Pomelo Pl Complete
Alta Vista & Pomelo Ave to 960 Pomelo Ave 5/24/21 – 6/9/21
904 Pomelo Ave to 950 Pomelo Ave 6/15/21 – 7/1/21
*Watermain and reclaimed water mains to be installed after the gravity sewer.
Phase 2: Lift Station 87 Structure
Pre-construction work began in October 2017. Lift Station 87 became operational in October 2020. Final completion scheduled for November 2020.
Phase 1: Lift Station 87 Microtunneling
This critical project element began in January 2017 and was completed in June 2017.