Schedule

To protect the City’s investment and minimize risks, construction will be completed in three phases. Schedules for the three phases overlap to maintain an aggressive schedule and minimize the overall construction duration.

Phase 3: Open Cut Pipeline Installation Sequencing & Scheduling

Date Updated: October 9, 2020
The following dates are estimated and subject to change based on weather or unforeseen conditions:

2020

  • October 8 – October 31:  Osprey Ave. from Lincoln Park Dr. south to 963 Osprey Ave (24-inch sewer, water main and intersection)
  • November 6 – December 19: Osprey Ave. from Bahia Vista to Alta Vista (8-inch water)
  • November 1 – December 3: Osprey Ave. from 963 Osprey Ave. to Alta Vista (24-inch sewer)
  • December 4 – December 19:  Alta Vista from Osprey Ave. to 1753 Alta Vista (24-inch sewer)
  • December 20 – January 3: No Work Scheduled – Holiday Break.

2021

  • January 4 – January 26: Alta Vista from 1753 Alta Vista west to 1742 Alta Vista Street (24-inch sewer).
  • January 28 – March 3: Alta Vista from 1742 Alta Vista Street to Pomelo Ave (24-inch sewer)
  • March 3 – March 17:  Pomelo Ave. from Alta Vista to Pomelo Place (8-inch sewer)
  • March 17 – April 7: Pomelo Ave. from Pomelo Place to end (8-inch sewer)
  • April 9 – April 21: Pomelo Place (8-inch sewer) 
  • April 27 – May 1: Lift Station 7 decommissioning
  • April 21 – June 24: Lift Station 7 demolition and park installation
  • April 14 – May 26: Pomelo Place & Pomelo Ave:  Water Main, Reclaimed Water Main, Storm Water Piping.

Phase 2: Lift Station 87 Structure

Pre-construction work began in October 2017. Lift Station 87 became operational in October 2020.  Final completion scheduled for November 2020.

Phase 1: Lift Station 87 Microtunneling

This critical project element began in January 2017 and was completed in June 2017.